Client: John Sisk & Sons (Holdings) Ltd Scaffolding: 10,410m2 Duration: 52 weeks Scaffold to external structure and internal areas of sports hall, library and classrooms. The site for the new school is on the northern edge of Wicklow Town and the building ranges from single storey to three storeys in height. Accommodation comprises of 25 …
Client: Bam Building Ltd Scaffolding: 9,800m2 Duration: 52 weeks Scaffold for new construction of seconday school to accommodate 900 pupils with floor area of 9,800 sq. m. Scaffold completed to the full external perimeter along with scaffold to PE hall, internal of all rooms, staircores, liftshafts and services buildings.
Client: Bam Building Ltd Scaffolding: 10,000m2 Duration: 52 weeks Scaffold for new construction of seconday school to accommodate 1000 pupils with floor area of 10,000 sq. m. Scaffold was completed to the full external perimeter along with scaffold to PE hall, internal of all rooms, staircores, liftshafts and services buildings.